projects

Costco Hatchery

Fremont, NE
97,782 SQ FT
Costco Wholesale
Mechanical Construction

MMC Contractors was awarded the full mechanical and plumbing scope for both the core and the shell of this project. Our team had all three trades onsite throughout the project.

The hatchery process begins by receiving eggs from surrounding areas, then they are incubated for approximately 19 days before being moved to hatchers. Once the chickens are hatched, they are sent to farmers to be raised.

Additional Project Information:

General Contractor: Graham Construction
Project Architect: MG2
Project Engineer: Scott C. Woods & Associates and Soteck

Related Projects

Featured image for Altus Commerce Buildings A, B, & C
Industrial

Altus Commerce Buildings A, B, & C

Des Moines
Featured image for Costco Chicken Plant
Industrial

Costco Chicken Plant

Omaha
Featured image for Liberty Waste Water Treatment Facility
Federal Government & Public Works

Liberty Waste Water Treatment Facility

Kansas City
Background for Portfolio CTA

Ready to talk shop?

Any questions you need answered, or folks you want to chat with, our team is eager to lend an ear.