Connect with us:

 

Mission Critical
AT&T Data Center IDC II

This project consisted of approximately 37,000 SF of new data center space on the third floor of an existing building hosting several other data centers. The project included installation of 36 CRAC units and three air-cooled chillers on the roof.

The project also included the furnishing and installation of three CHW pumps, five rooftop AC units, and approximately 3,500 LF of glycol chilled water piping.

MMC Contractors assisted in the design and development of the high-density pilot program for AT&T. We custom-fabricated eight, 650-gallon thermal storage tanks to fit within the confines of the space. 90% of the CHW piping in the facility was prefabricated in our New Jersey fabrication shop.

Subcontracted work: sheet metal, insulation, test and balance, and water treatment, as well as commissioning assistance. Construction began in April 2009 and was completed within 11 months.


Additional Project Information:

Square Feet: 37,000
Project Location: Totowa, New Jersey
Project Owner: AT&T
Field Office: Somerset