VA Medical Center Phase V
VA Medical Center Phase V – Administration Building & Education Center Addition; Expansion to the existing Central Energy Plant.
Square Footage: Admin Bldg & Education Center Addition – 84,200SF, 3 story addition to the existing facility.  CEP Addition – 2,900SF single story addition to the existing CEP.
 
Admin. Bldg. – Complete 4 pipe HVAC system, including steam to hydronic heat exchanger system, chilled water piping, ductwork and air handling units.  
 
CEP Addition – Provide an additional 1,200 ton chiller, with matching cooling tower and associated piping up to 24” in diameter.

Additional Project Information:

Project Location: Las Vegas, Nevada
General Contractor: Walsh Construction / Archer Western
Project Architect: Engineer: JBA
Field Office: Las Vegas