Connect with us:

 

Pharmaceutical
Sanofi-Aventis Utility Separation

 

MMC Contractors was selected as the Construction Manager to oversee all trades and perform the separation of the Central Utility Building for the Sanofi-Aventis campus for the new occupants. As several buildings are now owned and occupied in part, by the Cerner Corporation in addition to Sanofi-Aventis, the Campus Central Utility Plant required major modification in order for each company to operate independently from the other. MMC Contractors originally constructed the facility in mid-1980’s for Marion Laboratories (now Sanofi-Aventis) and has provided regular plumbing, process piping, millwright and general construction at the facility since it was built.

As Construction Manager our scope included all phases of demolition and construction including, installation of  a new 5,200-ton chiller plant which included chillers, pumps, piping, cooling towers, AHU’S, electrical, concrete, painting, piers and controls. Four (4) new boilers were added to existing boiler plant including pumps, electrical, piping, DA tanks, concrete work and painting. 

We separated all electrical and water utilities between all the buildings because the each building now has different owners. We also relocated 2 generators and brought in new electrical service. We drilled over 40 concrete piers 30’ deep and 5’ diameter to provide support for new cooling tower cells. A new separation wall including mechanical, electrical, drywall, carpet and painting completed the project that took 9 months to complete.

The project won an Outstanding Mechanical Installation (OMI) Award in 2008-2009.


Additional Project Information:

Project Location: Kansas City, Missouri
Project Owner: Sanofi-Aventis
Field Office: Kansas City